Tuesday, April 18, 2017

Bricks & Geothermal Wells Progressing

North Side Brick Work

With the arrival of spring weather, work on the David "DJ" Sokol Living for Life Building is picking up momentum.

The brick layers are moving along on the the north side and turning the corning on the front.  The race is on for the other crews to keep ahead of them.

Cement floors are completed in the two-story section of the building and they are pushing hard on getting the remainder or the steel up in the Southeast corner.

Southwest of the building the geothermal well field is nearing completion.