Construction Video September 16-October 15


It a was better month weather-wise for construction.  The day after September's Fall Festival, the first load of steel arrived. Besides steel for the two story portion of the building, cement slabs were set in place on the cinder block tornado shelter.

Construction is currently about a month behind schedule because of all the rain we had this summer.  Hopefully mother nature cooperates the next couple of months so that the building can be enclosed before a predicted wet winter with a delayed spring gets underway.