Also Watch the entire construction Time-Lapse since May 2016. Duration 7:17
Monday, February 27, 2017
Mid January - Mid February Time Lapse Construction
Friday, January 20, 2017
Mid December thru Mid January Time Lapse Video
The weather has been good for January. We did have some very icy days but generally not to bad. The most visible change has been the adding of precast stone along the roof line. The one-story portion of the building has yet to begin.
Friday, December 16, 2016
Mid November thru Mid December Time Lapse
The second floor has been poured and the framing of the 2nd floor exterior wall is progressing. Steel for the south wing is on site. Construction is running behind about one month so the hope is the building will be totally enclosed by the end of January.
Tomorrows low is predicting to be -10 degrees.
Wednesday, December 7, 2016
2nd Floor and What's Next
Additional Photos![]() |
![]() |
![]() |
Plumbing in the ground for the 2 story wing is almost ready for inspection and then electrical work in the ground will begin.
The south wing soon to be started will be impressive in that it actually has a larger foot print than what has been built up to this time.
Monday, November 21, 2016
Mid October thru Mid November Time Lapse Video
Much of the steel frame is now completed for the two story portion of the building. They will soon pour the the 2nd floor.