Construction is currently about a month behind schedule because of all the rain we had this summer. Hopefully mother nature cooperates the next couple of months so that the building can be enclosed before a predicted wet winter with a delayed spring gets underway.
Monday, October 17, 2016
Construction Video September 16-October 15
Construction is currently about a month behind schedule because of all the rain we had this summer. Hopefully mother nature cooperates the next couple of months so that the building can be enclosed before a predicted wet winter with a delayed spring gets underway.
Wednesday, September 21, 2016
Time Lapse 30 Days of Construction
Lots of rain the last month but construction continues to move along. The structure so far consists of the elevator shaft and the portion designated as a force 3 tornado shelter which consists of the study hall and one religion classroom. The day after this video was completed a load of steal arrived and was unloaded so expect some major progress coming soon.
Monday, August 29, 2016
Time Lapse Construction Video #2
Video #2
July 8, 2016 -August 15, 2016
July 8, 2016 -August 15, 2016
Wednesday, August 10, 2016
Walls Sprout as Elevator Shaft Rises
![]() |
More Photos: Elevator Shaft Rises - 1st Walls Go Up |

To help give you perspective here are 2 diagrams.
The first is a satellite image with the outline of the building superimposed. The main entrance lines up with the DJ Sokol Chapel and the south entrance to the science and math wing lines up with the south door dorm entrance.
This 2nd Diagram is a blue print indicating the location of current construction highlighted in yellow.
Thursday, July 28, 2016
Excavation: Time Lapse
May 18, 2016 - July 8, 2016